Project development · Illustrative scenario
A power fix changes the promise
01 / The objective
What the organization needs to achieve
Deliver a 100-megawatt building to the anchor tenant by Q3 2028.
A data center developer–owner–operator is building a $5b data center for a hyperscale anchor tenant. The developer will provide and operate the facility’s power and cooling infrastructure; the tenant will operate its computing equipment.
Achieving this objective depends on actions by independent stakeholders outside the developer’s control:
Independent stakeholders
- Anchor tenant
- Electric utility
- County board
- Water provider
- State air regulator
- Community groups
02 / What changes
Grid power is delayed
External stakeholders
- Electric utility
Internal teams
- Utilities development
03 / The operational response
Engineering proposes gas turbines
Internal team
- Engineering
Internal team
- Environmental permitting
Environmental permitting’s response
Prepares the application for turbine operations
The proposed power solution introduces an air-permitting dependency.
04 / The existing commitment
The county was promised grid power
Internal team
- Government relations
External stakeholder
- County board
The earlier assurance
Grid power for normal operations. Generators for emergencies only.
The county expects generators to be used for emergencies only.
05 / The conflict
The permit filing exposes the contradiction
Air permit application
Turbines proposed for normal operations
Earlier county assurance
Generators for emergencies only
External stakeholders
- Community groups
External stakeholder
- County board
Project approval and delivery are at risk.
06 / How SCI helps
Before the permit is filed
Proposed power solution
Temporary turbines and the air permit application
Existing assurance
Grid power, with generators for emergencies only
SCI weekly report
Strategic Communications Brief (SCB)
Brings relevant changes and existing commitments together for leadership review.
Internal leadership
Leadership review
A common basis for deciding how to respond.
Review the turbine proposal against the county assurance before filing.
